Tidewater Avenue is getting new pavement from Ferry Street to Breakwater Road. Work starts next week and takes about 6 weeks if the weather holds.
What crews will do
- Grind off the worn surface and lay new asphalt, 2 or 3 blocks at a time.
- Rebuild the curb ramps at 14 corners so they are easier to use with a wheelchair, a walker or a stroller.
- Repaint the crosswalks and bike lanes.
What changes while they work
| If you | What to expect |
|---|---|
| Drive on Tidewater Avenue | 1 lane stays open each way. Expect short waits where a flagger is directing traffic. Crews work Monday to Friday, 7 a.m. to 5 p.m. |
| Park on the street | No parking on a block while it is paved. Signs go up 3 days before. A car left on a signed block may be towed. |
| Live on the street | You may not be able to use your driveway for up to 4 hours while new asphalt cools. Crews knock on doors the day before. |
| Ride the bus | Stops on Tidewater Avenue move to the nearest side street. Look for a temporary sign at your stop. |
| Walk or use a wheelchair | Sidewalks stay open. A marked detour takes you around each corner while its curb ramp is rebuilt. |
| Run a business | Businesses stay open, and your customers can reach your door at all times. Tell us your delivery hours so we can plan around them. |
| Put out trash | Put your carts out by 7 a.m. as usual. If your block is closed, crews carry the carts to the truck. |
What it costs
The project costs $2.1 million. It is paid for from the street repair fund in the adopted budget.
What you can do
- Join the Tidewater Avenue paving open house to ask the project team a question.
- Move your car when the no parking signs go up on your block.
- Call Public Works at 555 555 0140 or email publicworks@cedarharbor.example with a question or a concern.
- Tell us about a problem at the work site on the Report a problem page.